A typical Hann Cabinet kitchen takes 5–8 weeks from first consultation to handover. Here is the schedule we commit to in writing.

Week 1–2: Design & confirmation

Site measurement, 3D design revisions and final itemised quotation. No deposit on production until you sign off the drawings.

Week 3–5: Factory production

Carcasses, doors and worktops are fabricated in our own factory while hacking, plumbing and tiling proceed on site.

Week 6–7: Installation

Most kitchens install in 5–10 working days, followed by worktop templating, quartz installation and accessory fitting.

Week 8: QC & handover

Joint inspection, hinge adjustment, silicone touch-up and a 10-year warranty card.

Planning tip: order appliances early — hob cut-out sizes must be confirmed before the worktop is cut.

— Hann Cabinet, bespoke kitchen & wardrobe specialists in the Klang Valley. Get a free 3D design & quote.

FREE 3D DESIGN

See your kitchen before you spend a sen.

GET FREE QUOTE
admin

WRITTEN BY

admin

Workshop-trained designers with 12+ years of cabinetry experience across the Klang Valley.