A typical Hann Cabinet kitchen takes 5–8 weeks from first consultation to handover. Here is the schedule we commit to in writing.
Week 1–2: Design & confirmation
Site measurement, 3D design revisions and final itemised quotation. No deposit on production until you sign off the drawings.
Week 3–5: Factory production
Carcasses, doors and worktops are fabricated in our own factory while hacking, plumbing and tiling proceed on site.
Week 6–7: Installation
Most kitchens install in 5–10 working days, followed by worktop templating, quartz installation and accessory fitting.
Week 8: QC & handover
Joint inspection, hinge adjustment, silicone touch-up and a 10-year warranty card.
Planning tip: order appliances early — hob cut-out sizes must be confirmed before the worktop is cut.